119
=S=> BGB 645. 1 If the work , before acceptance , is destroyed or deteriorates or becomes impracticable as the result of a defect in the materials supplied by the customer or as the result of an instruction given by the customer for the carrying out of the work , without a circumstance for which the contractor is responsible contributing to this , then the contractor may demand a part of the remuneration that corresponds to the work performed and reimbursement of those expenses not included in the remuneration . The same applies if the contract is cancelled under section 643.
=S=> BGB 645. 2 A more extensive liability of the customer for fault is unaffected .
|