105
=S=> BGB 642. 1 If , in the production of the work , an act by the customer is necessary , then the contractor may demand reasonable compensation if the customer , by failing to perform the act , is in default of acceptance .
=S=> BGB 642. 2 The amount of compensation is assessed on the one hand on the basis of the duration of the default and the amount of the agreed remuneration , and on the other hand on the basis of what expenses the contractor saves or what the contractor can earn by employing his working capacity elsewhere .
|